我的游泳池施工方案 希望對你有參考價值(一)

2011-12-30 08:37:45  來源:游泳池施工方案  字號:【奶茶視頻在線觀看:  奶茶視頻在線觀看:  奶茶視頻在線觀看:】  瀏覽:67

一、方案依據

《網(wang)球(qiu)場(chang)——游泳(yong)池招標書》

《網球(qiu)場——游泳池》建施1/2,2/2及(ji)結施1/2,2/2

《網球場巖(yan)土(tu)工程勘察報告(gao)》

《水(shui)工混凝土施(shi)工規范》SDJ207-82

《建筑裝飾工程(cheng)施工及驗收(shou)規范》JGJ73-91

《建筑地面工(gong)(gong)程(cheng)施工(gong)(gong)及驗(yan)收(shou)規范(fan)》GB50209-95

《建筑(zhu)工程質量檢驗評定標準(zhun)》GBJ301-88

現行建筑施工其它(ta)相關規劃

 

二、工程概況

    本游泳池系公園的一(yi)部分,位于(yu)北街南側,在原網球場一(yi)層平面(mian)(mian)(A)-(G)、⑤-⑧軸區(qu)域(yu)內建造(zao),游泳池(chi)(chi)(chi)尺寸(cun)25m×12m,深度1m~2m,采用(yong)(yong)(yong)鋼(gang)筋砼結構,底(di)板厚300,池(chi)(chi)(chi)壁250,砼強度等級C25,抗滲S6,池(chi)(chi)(chi)內裝修為泳池(chi)(chi)(chi)專用(yong)(yong)(yong)面(mian)(mian)磚貼面(mian)(mian),池(chi)(chi)(chi)外四周(zhou)地(di)面(mian)(mian)為防滑地(di)磚面(mian)(mian)層,泳池(chi)(chi)(chi)配套用(yong)(yong)(yong)給水、排水、供(gong)配電設施配合施工(gong)、穿插進行,以(yi)達竣(jun)工(gong)即可(ke)動用(yong)(yong)(yong)。

 

三、施工部署

3.1  施(shi)工組織

    成立游泳池工(gong)(gong)程項目組,設項目經理兼技術負(fu)責人(ren)1人(ren),施(shi)工(gong)(gong)員2人(ren),質檢員、安全員、材料員各1人(ren),選用木工(gong)(gong)、鋼筋、砼及(ji)裝飾、水電5個班組,

3.2  主要(yao)指標:

    工(gong)期:計劃工(gong)期50d(日歷天)

質(zhi)量:確保(bao)合(he)格,力(li)爭優(you)良。

安全:無重(zhong)大安全事故

3.3  施(shi)(shi)(shi)工安排:鋼筋(jin)砼池(chi)(chi)分二步(bu)施(shi)(shi)(shi)工,第(di)一(yi)步(bu)施(shi)(shi)(shi)工底板,第(di)二步(bu)施(shi)(shi)(shi)工池(chi)(chi)壁,底板以上100處設施(shi)(shi)(shi)工縫,砼泳池(chi)(chi)施(shi)(shi)(shi)工完后,進入裝修。

3.4  協調管(guan)理

    公(gong)司主動(dong)協調與(yu)業(ye)主、監(jian)理、設計、質監(jian)等單位的(de)聯系(xi),做好施工中的(de)主動(dong)聯系(xi)工作,特別對需(xu)報驗(yan)的(de)有關資料,項目(mu)應(ying)積極主動(dong)按時(shi)或提前報出(chu),給施工創造和諧(xie)環境。

 

四、施工準備

4.1  施工場地道路準備

a) 平(ping)整場(chang)地(di):凡高低不平(ping)等場(chang)地(di)及障礙物清除,便于放線;

b) 修筑臨時道路(lu):可按(an)簡易三級(ji)道路(lu)修筑以便(bian)材料機具等運進施工場(chang)地;

c) 臨時設施準備:擬向甲方租用網球場一層200~300m2,供住宿及(ji)放(fang)料用,因工期短(duan),擬不搭設(she)臨(lin)建,需取得許(xu)可。

4.2  施工用水

    按甲(jia)方的(de)提(ti)供(gong),自原網球場(chang)一(yi)層北側外接一(yi)φ60給水管至工地,供(gong)施工用水。

4.3  施工用電

    自原網球場一層南側接一電源,采用BV型銅芯塑料線35mm2及25 mm2各一條(tiao),至施(shi)工場(chang)地,可滿(man)足供(gong)電。

4.4  做好鋼材、水泥、砂、碎石檢驗及砼配合比試配。

 

五、主要施工方法

本工程(cheng)工藝流(liu)程(cheng)圖(tu):

土方開(kai)挖(驗槽)→300厚砂(sha)石墊層→C10墊層砼(tong)→底板鋼(gang)筋綁(bang)扎、池(chi)壁豎筋預留→池(chi)壁100高支模→底板澆砼(tong)→養(yang)護→池(chi)壁綁(bang)扎鋼(gang)筋→池(chi)壁支模板、套(tao)管預埋→池(chi)壁澆砼(tong)→養(yang)護、拆模→池(chi)內(nei)側壁、池(chi)底及(ji)池(chi)外地面裝修(xiu)、安裝穿插(cha)施(shi)工。

5.1  池(chi)坑(keng)土方開挖

池坑土(tu)方(fang)采用一臺(tai)反鏟挖掘機挖土(tu),一臺(tai)裝載機裝運(yun)土(tu),4臺(tai)自卸(xie)汽車運(yun)土(tu),計劃二天內完成土(tu)方(fang)開挖及運(yun)輸。土(tu)方(fang)開挖:最深約2.70m,淺1.70m,基底坑面積為15.0m×28.0m,并按Ⅱ類(lei)土(tu)放坡。

本(ben)地(di)基土(tu)據地(di)勘(kan)報(bao)告下部有淤泥質粘(zhan)土(tu),游(you)泳池底部面(mian)積大,很(hen)難避免不遇上該土(tu)層,為(wei)此,本(ben)挖(wa)土(tu)方考慮1/4的(de)挖(wa)方量為(wei)淤泥質粘(zhan)土(tu)。

5.2  基坑支護(hu)

    基坑(keng)開挖(wa)后,為避免坑(keng)壁(bi)雨水(shui)沖刷(shua)、崩潰,對坑(keng)壁(bi)采用抹(mo)20厚1:3水(shui)泥砂(sha)漿(jiang)保護層,局部(bu)薄弱土壁(bi),釘以(yi)φ6筋@200縱(zong)橫布置(zhi),長(chang)度(du)200~250。如不抹(mo)水(shui)泥砂(sha)漿(jiang)亦可將(jiang)坑(keng)壁(bi)放坡系數加大(da),改(gai)按1:0.8,土方挖(wa)量則增大(da)。

5.3  基坑排水(shui)(shui)(shui):沿基坑四周邊沿設200寬、300深排水(shui)(shui)(shui)溝,水(shui)(shui)(shui)溝采用(yong)紅(hong)磚M5水(shui)(shui)(shui)泥砂漿砌(qi)筑,并每隔10m左右設集水(shui)(shui)(shui)坑,集水(shui)(shui)(shui)坑500×500×800均用(yong)紅(hong)磚砌(qi)筑,集水(shui)(shui)(shui)坑底比(bi)泳池底低500左右。

5.4  墊層(ceng)施工

a) 墊(dian)層(ceng)施工前,須在(zai)素土夯(hang)實的(de)基礎上回填300厚砂石墊(dian)層(ceng),擬(ni)以淋水灌(guan)實;

b) 澆100厚C10砼(tong)墊層(ceng),以(yi)平板(ban)振動(dong)器搗固(gu),墊層(ceng)四周(zhou)須立模板(ban),墊層(ceng)比底板(ban)寬(kuan)出100。

5.5  泳(yong)池(chi)底板施工

5.5.1  鋼(gang)筋綁(bang)扎

鋼(gang)(gang)筋(jin)(jin)采用現(xian)(xian)場制(zhi)作(zuo),現(xian)(xian)場綁扎,底板(ban)(ban)為雙層(ceng)(ceng)鋼(gang)(gang)層(ceng)(ceng),上、下(xia)層(ceng)(ceng)鋼(gang)(gang)筋(jin)(jin)間設φ18門型(xing)撐筋(jin)(jin),撐筋(jin)(jin)腳各相反(fan)向彎80,間距按菱形設置(zhi),每(mei)平方米一支,底板(ban)(ban)下(xia)層(ceng)(ceng)筋(jin)(jin)保護層(ceng)(ceng)35mm,其余(yu)25mm,其它操作(zuo)見施工質量計劃和程序控制(zhi)文件,為便于池壁(bi)(bi)模板(ban)(ban)安裝,擬在離(li)池壁(bi)(bi)1.0m~1.6m距離(li)予(yu)焊些φ18鋼(gang)(gang)筋(jin)(jin)頭伸(shen)出板(ban)(ban)底表面100,@1200~1500。

5.5.2  模板安(an)裝(zhuang)

    底板(ban)厚(hou)度300,四周模板(ban)采用(yong)18厚(hou)膠合板(ban),配合45×100松(song)(song)(song)枋(fang)以及50×50木樁等固定,池(chi)壁100高模板(ban)直接(jie)(jie)用(yong)45×100松(song)(song)(song)枋(fang),支(zhi)撐于(yu)鋼筋骨(gu)架上,豎向采用(yong)鋼筋頭焊接(jie)(jie)于(yu)底板(ban)上層篩上,再用(yong)14#鉛(qian)絲綁牢,松(song)(song)(song)枋(fang)下部(bu)需(xu)墊(dian)(dian)有25厚(hou)水泥墊(dian)(dian)塊,模板(ban)安(an)裝后(hou)需(xu)最(zui)后(hou)檢驗,合符圖紙尺(chi)寸后(hou),才進入下一道(dao)工(gong)序。

5.5.3  砼施工

    底(di)板(ban)砼(tong)(tong)(tong)(tong)C25普通密(mi)實性防水砼(tong)(tong)(tong)(tong),抗(kang)滲等級S6,砼(tong)(tong)(tong)(tong)中摻10%UEA膨脹(zhang)劑(ji);砼(tong)(tong)(tong)(tong)澆灌前須搭設馬凳、鋼(gang)管(guan)架道,禁(jin)止(zhi)直接在鋼(gang)筋網上鋪腳手板(ban)行走,底(di)板(ban)砼(tong)(tong)(tong)(tong)一次澆完,中間不(bu)間歇,注意振搗密(mi)實,底(di)板(ban)砼(tong)(tong)(tong)(tong)完后(hou)養(yang)護3d,再進行池(chi)壁施工。

5.6  池壁施工(gong)

池(chi)壁厚250mm,高度1.0m~2.0m

a) 模板:采用18厚膠合板,豎(shu)向(xiang)45×100松枋@500,橫向(xiang)兩側用2φ48鋼(gang)管(guan),3型扣φ14止水螺栓,管(guan)豎(shu)向(xiang)間距600,螺栓水平向(xiang)間距500,上下排相互錯(cuo)開,內壁模支撐可利用予埋鋼(gang)筋頭(tou)靠木枋固定;

b) 鋼筋(jin)(jin):池壁(bi)鋼筋(jin)(jin)在底(di)板扎筋(jin)(jin)中已予埋豎筋(jin)(jin),此時只需將豎筋(jin)(jin)間(jian)距調整,綁扎水(shui)(shui)(shui)平筋(jin)(jin),水(shui)(shui)(shui)平筋(jin)(jin)均(jun)綁扎在里側(ce),并扎上S型(xing)拉(la)筋(jin)(jin),按豎筋(jin)(jin)的(de)雙(shuang)倍(bei)間(jian)距綁扎,上下排錯開,為(wei)保持壁(bi)厚250尺寸不變(bian),可在止(zhi)水(shui)(shui)(shui)穿(chuan)壁(bi)螺栓(shuan)(shuan)上焊(han)(han)兩(liang)根φ8并與(yu)螺栓(shuan)(shuan)垂直的(de)短筋(jin)(jin),2短筋(jin)(jin)φ8的(de)間(jian)距250mm,或在雙(shuang)層鋼筋(jin)(jin)網上按螺栓(shuan)(shuan)距離焊(han)(han)250長的(de)φ14筋(jin)(jin)亦可;

c) 壁與底(di)施(shi)工(gong)縫(feng)處(chu)理:

壁扎(zha)筋(jin)支模(mo)前(qian),對池壁已澆(jiao)100高(gao)度(du)的砼(tong)水(shui)(shui)平面(mian),認真進行沖(chong)刷(shua),沖(chong)洗,模(mo)板(ban)配置(zhi)時,對施工縫處,外側(ce)留(liu)150寬活動模(mo)(類似柱(zhu)模(mo)中的柱(zhu)腳清(qing)掃(sao)口),待(dai)模(mo)板(ban)、鋼筋(jin)安裝完成,澆(jiao)砼(tong)前(qian)2h,再次沖(chong)洗,擺放好BW硅(gui)橡膠(jiao)止(zhi)水(shui)(shui)條后,再釘上(shang)活動側(ce)模(mo),隨(sui)即澆(jiao)砼(tong),BW止(zhi)水(shui)(shui)條擺置(zhi)于壁厚的中部,通圈(quan)設(she)置(zhi),砼(tong)澆(jiao)搗后遇水(shui)(shui)膨脹,起隔水(shui)(shui)、止(zhi)水(shui)(shui)作用。

d) 砼(tong)(tong)(tong)澆(jiao)灌:池壁砼(tong)(tong)(tong)澆(jiao)灌前需認(ren)(ren)真沖洗(xi)施工縫(feng)處的(de)砼(tong)(tong)(tong),并按要求置(zhi)放(fang)BW硅(gui)橡膠止水(shui)條,要全長設置(zhi),不許(xu)中斷,池壁砼(tong)(tong)(tong)每次澆(jiao)注高度以500~600為宜,向一端推移,達(da)到基(ji)本保水(shui)泌水(shui)后,再澆(jiao)第二(er)輪,振搗均勻,不得(de)搗固時間過長,避(bi)免跑漿、脹模(mo),砼(tong)(tong)(tong)澆(jiao)完后,認(ren)(ren)真養護(hu),特別是豎向砼(tong)(tong)(tong)要著重養護(hu),擬用舊麻(ma)袋片(pian)澆(jiao)濕覆蓋,始終保持濕潤,連續養護(hu)不少于7d。

5.7  裝修(xiu)工程(cheng)

    裝(zhuang)修(xiu)施工前(qian)須對泳池蓄水48小時試驗(yan),灌水后池壁外(wai)表面不得出(chu)現陰濕,每晝夜水量損耗小于(yu)每方(fang)2升,以檢驗(yan)砼的抗(kang)滲效果,確不滲漏(lou),才(cai)進行裝(zhuang)修(xiu)施工,否則需(xu)采取措施,直(zhi)至不滲水為(wei)止,再進入裝(zhuang)修(xiu)。

5.7.1  池(chi)壁、池(chi)底裝修

(1)池(chi)底、池(chi)壁套方、打底:為找平層抹灰提供依據;

(2)找平層:1:2水泥防(fang)(fang)水砂(sha)漿找平層,摻5%防(fang)(fang)水劑,最薄處15厚;

(3)面(mian)磚結合(he)層(ceng):采用(yong)5厚1:水泥砂漿(jiang)結合(he)層(ceng);

(4)貼泳池專用面磚(zhuan),貼磚(zhuan)前(qian),經彈(dan)線、分格、選(xuan)磚(zhuan)、浸泡(pao),特別對(dui)池角的轉角磚(zhuan)要下(xia)功夫重點(dian)貼好。

5.7.2  泳池外地面裝修(xiu)

池內面磚貼完(wan)后再貼地面的(de)防滑地磚,池外壁(bi)需用(yong)20厚1:2防水砂漿抹(mo)灰壓光后再行回填土,其(qi)施工順(shun)序為(自下至(zhi)上):

(1)回(hui)填土(tu)夯(hang)實;

2)300厚砂石回(hui)填(tian)層;

(3)100厚C10砼墊層(ceng);

(4)20厚(hou)1:2水泥砂漿找平層;

(5)5厚1:1水泥砂漿結合層;

(6)防滑地磚面層。

5.7.3  泳池及地面裝飾(shi)工程質量(liang)標(biao)準

(1)池壁內側面磚:保證項目、基(ji)本項目符合(he)要求,允許偏差(cha):

表面平(ping)整2mm;立面垂直2mm;陽(yang)角(jiao)方正2mm;接縫(feng)(feng)平(ping)直2mm;接縫(feng)(feng)高(gao)低0.5mm;

(2)池底面磚:保證項目、基本(ben)項目符合要(yao)求、允許偏差:

表面平(ping)整2mm;縫格平(ping)直3mm;接縫高低差0.5mm;面磚間(jian)隙寬度不大于2mm;

(3)地面缸磚:

保證項(xiang)目、基本(ben)項(xiang)目符合要(yao)求,允許(xu)偏差:

表面平整4mm;縫格平直3mm;接縫高低差(cha)1.5mm;地(di)磚間隙寬度不大于(yu)2mm;

  